We acquired a project at Prime Focus World wherein we have installed & implemented the solution as follows:

1. Internet Connectivity: Around 365 workstations were to be created wherein each one gets the connectivity for the each workstation,we took the turnkey project of laying the cat6 STP cable of DLINK wherein the server rack/Network rack was in the basement and each panel of CAT6 was terminated with Systimax I/O’s and Patch Panel

.2. The project on the passive components was made live in 21 days.



3. The WIFI-Connectivity was also established in entire premises.






» The Electrical Work

1. UPS- We established the SLD diagram and accordingly layed the UPS power cable to 365 workstations.






2. Raw Power: With each workstation the raw power was given for charging of mobile phones etc at each and every workstation.






3. MSEB Power: We increased the MSEB power from 40KW to 100KW through MSEB .







4. Panel – RYBN- The panel for the UPS power supply was installed.







5. UPS 100KVA- this was installed for backup of power generation.








» Security

1. The CCTV/Survellance system was installed at the premises with 32 IR cameras,DVR’S etc,automatic backup,display on mobile